Warner Budget Committee

Meeting Minutes

Thursday, December 4, 2008

 

Meeting opened at 6:04 p.m.

In attendance:   Marc Violette – Chair

                        John Warner – Vice Chair

                        Mike Cutting

                        Clyde Carson

                        Harold Whittemore

                        Brenda O’Brien

                        Peter Newman – Warner Village Water District Representative

                        David Karrick Jr. – Selectman’s Representative

Absent:             None                  

Others present:

David E. Hartman – Selectman                             Peg McLaughlin – WVWD Administrative Assistant

Phil Lord – WVWD Commissioner             Martha Mical

Jim McLaughlin – WVWD Clerk  

Mr. Violette learned that the County budget for 2009 increased by 1.5%.  Mr. Violette also informed the Committee that on December 16th there will be a hearing on the school budget held at the High School.   

1. Warner Village Water District 2009 Proposed Budget

Mr. Violette requested that budgets be presented to the BC before the scheduled meeting to allow time for review.   

General Government

Mr. Lord explained that the budget increased by 1.4% from last year.  The largest change is within the General Government budget.  Sewer System has decreased as well as Capital Outlay.  Mr. Lord explained that up through November, 91% of the budget has been spent.  Mr. Lord explained there is an increase in the General Government budget that is related to the cost of billing software for $3,800, the cost of an audit for $8,000 and employee benefits.  

Questions:

Mr. Violette asked if WVWD can be included with the Town’s auditing firm.  It was explained that the Town’s auditing firm is not interested.  

Mr. Violette asked if the WVWD pays 100% of employee benefits.  Mr. Lord said yes, it’s the same plan as the Town.  Mr. Violette asked why the Town’s insurance cost went down and the WVWD increased.  Ms. McLaughlin was not aware of any negotiated changes.  Mr. Violette asked the WVWD to contact Laura Buono for the changes the Town made.   

Mr. Carson asked the size of the WVWD staff.  Mr. Lord said 2 full time employees and an Administrative Assistant.   

Mr. Cutting asked how the salaries are broken down between water & sewer.  Ms. McLaughlin explained in General Government there is her salary as well as the Commissioners, the Clerk and the Treasurer.  For water & sewer the two employees are split 70% sewer, 30% water.  Mr. Cutting asked how much the Commissioners make per year.  Mr. Lord said $1,200.   

Mr. Violette asked why the WVWD audit cannot be included with the Town’s audit firm.  Ms. McLaughlin said it has to do with the lack of personnel.   Mr. Lord said WVWD is in the process of looking for an auditor and will return with an update. Mr. Warner recommended checking with the Library.  Mr. Violette recommended that the Selectmen speak to Laura Buono about including the WVWD in the next audit bid.  Can the WVWD be included, if not, why.  

Mr. Cutting asked if software update is going to be a yearly expense.  Ms. McLaughlin explained the software will allow for different modes.  This software can be used for current customers as well as future customers.   Ms. McLaughlin explained that first changes to the billing need to be decided upon before the software is written.   Mr. Cutting feels that if the WVWD is not positive about changing the billing system then funding should not be in the budget.  Mr. Violette agreed if the WVWD cannot justify the cost the BC will cut it from the budget.  Mr. Warner said it was mandated by a public meeting to look into the billing software and asked what the status is of the WVWD deciding if they are going to use the software.  Ms. McLaughlin explained that Commissioner Perkins, who is not present this evening, has been doing the research on the billing software.  Mr. Violette said the WVWD will need to return with more information.  Mr. Newman added that since it was mandated at the last WVWD annual meeting to look into the billing software that further approval would need to be granted at the next annual meeting.  Mr. Newman feels the funding needs to be in the budget whether it’s spent or not.  Mr. Cutting feels there are too many unanswered questions; the Commissioners should be coming to the BC with their decision that can be later decided upon by the voters.  Mr. Warner asked if there is any estimate on what the increase in revenue could be from using this software.  Topic was tabled until Commissioner Perkins is available.   

Sewer System

Mr. Violette asked how the WVWD came up with their fuel figure.  The cost per gallon used was not known.  Mr. Violette explained that the BC requested the Town to revisit their fuel costs which are budgeted for $4.00 per gallon as recommended by the State.  Mr. Violette is recommending the same for the WVWD.  This request is based on the recent cost reduction for the average consumer.    

Mr. Carson asked how the WVWD applies their surplus.  Ms. McLaughlin said surplus is applied to the tax rate.  

Mr. Violette asked why there is a $3,000 increase for propane.  Mr. Newman explained that the WVWD budgeted $2.699 per gallon for 2,400 gallons.  Ms. McLaughlin explained the WVWD is included in the Town’s contract.   

Brenda O’Brien asked about the tires budgeted for the 2008 Ford Ranger.  How many miles are on the vehicle?  Mr. Lord believes tires will be needed by the end of the year.  Ms. O’Brien pointed out that a set of new tires should last about 35,000 miles.  Mr. Lord will return with the amount of mileage on the 2008 Ford.  Mr. Lord further explained that there is one employee responsible for the entire precinct, he does live out of town and is on call 24/7.  

Mr. Lord said there is an increase in trucking costs for sludge removal.    

Mr. Lord explained that the WVWD learned from RSA 149-1:7 that the district can charge a surcharge on certain parts of the sewer system if it benefits only a few people.  A letter has been drafted for those businesses that use the pumping station at exit 9.  Since 2000 when the WVWD obtained ownership of the pumping station from McDonald’s maintenance costs amount to $29K.  The letter explains that the businesses will be charged a surcharge in the amount of $2.10 per 1,000 gallons.  Mr. Lord said the WVWD needs to speak with the Department of Revenue Administration on how to put the surcharge money into a separate account; $5,000 is estimated per year.  Replacing the pumping station would cost about $90K. Any new development at exit 9 will have their own pumping station. Mr. Violette noted that a new pumping station was not included to the CIP.  Mr. Violette recommended including such an expense next year.  Mike Cutting confirmed that an annual meeting is not needed to implement the surcharge.  

Mr. Violette spoke about line 13; $7,500 was budgeted only $3,300 has been spent to date.  Mr. Lord explained that another sludge pump needs to be built.  At this time the WVWD needs to find out the cost to replace a rotor.  Before that can be done a crane needs to be arranged to pull the rotor up and out.  Right now there is construction on Parade Ground Cemetery which is the only way to get a crane to the site, so it will be a couple of weeks before the rotor can be addressed.  Ms. McLaughlin added that the money could also be encumbered.  

Mr. Carson noted that line 7 has been overspent continually over the years.  In 2009 the line was decreased by $3,000 and he wonders if this is appropriate.  Mr. Lord explained why the line decreased and feels the amount is adequate.  

Water System

Wage increase for both employees is budgeted for 2009.   

Mr. Violette asked if line 4, Building Materials could be cut, based on history the line is always under spent.  $700 is budgeted and no more than $180 is spent for the past 5 years.  Mr. Violette asked the Commissioner to re-look at line 4 as well as line 11, System Maintenance.  

The BC and WVWD discussed why the precinct buys chemicals (chlorine) in bulk, is it economical in the long run.  The Commissioner explained that buying in bulk saves money and the material does not go to waste.   

Mr. Lord explained under System Maintenance they are looking to locate and replace all the curb stops.  This year because of budget constraints the project was put on hold, but next year WVWD would like to begin the project.  

Mr. Violette asked who takes care of the fire hydrants.  Mr. Lord explained that the WVWD maintains the hydrants in the summer months and the Highway Department takes care of winter maintenance.  Hydrant replacement is within the Fire Department budget.   

Mr. Warner asked Mr. Lord to explain the pattern of spending on line 11, is it necessary to budget $5K?  Mr. Lord said $5K is budgeted in case of a line break; it’s more of a contingency figure.  Mike Cutting confirmed that the budget has two contingency funds; the other is in General Government.  History reflects the bottom line is not under budget by very much.  

Clyde Carson asked if there is a type of mutual aid with other precincts.  Mr. Lord explained most towns run with minimum personnel; there is mutual aid set up for emergencies.   

Capital Outlay – Debt – Capital Reserve

Mr. Lord explained the bond principal for the new tank is down.  

Mr. Violette asked about the lease for the new truck.  Mr. Lord said the WVWD obtained a municipal lease; at the end of 4 years $1 is paid and ownership is obtained.  One payment is made a year in the amount of $4,982.92.  

Mr. Lord explained System Improvement includes meter replacement.  The program is a four year program, coming into the last year the WVWD decided to break the last year up; instead of $25K for meters in one year a figure of $15K (32 meters) was decided upon, the balance will go into a Capital Reserve for wells on North Village Road (4 wells for between $25K - $30K).   Mr. Cutting asked if there are new statistics with the new meters.  Mr. Lord said some households have gone up where others have gone down.  Mr. Cutting asked in 4 years the WVWD spent $79,123 for meter replacement, was this worth it.  Mr. Lord explained the State which inspects every 5 years said that meters need to be replaced.  Mr. Cutting’s point is the WVWD has not developed an extra $79K in revenue by adding new meters.  Mr. Carson asked if there are plans to update the meters so drive by readings can be done.  Mr. Lord said no, it’s very expensive.  Mr. Lord said for a new hand held reader the cost was $500, they were using a loaner.   

Revenue Estimates

Mr. Lord said Water Supply pulled in $106K ($65 is estimated).  Mr. Carson asked if there was an effort for water conservation reducing the amount of water going to the precinct how would that impact the precinct, for example energy saving toilets.  Mr. Lord said there would be an impact to the precinct in revenue, but there would be a savings on electricity and water.   

The WVWD will meet with the BC on December 18th at 6:00 p.m. to follow up on the questions that were brought up during this meeting; the BC will also meet with the Selectmen’s office.  

January meeting schedule will be determined on December 18th.   

Selectman Hartman informed the BC that bids were opened for the Connors Mill Bridge project.  There is also a minor construction project underway at the corner of Parade Ground Cemetery Road and West Joppa (Hazard Mitigation Project).  

Martha Mical heard some of the board members sent questions by email and she was wondering what those questions and answers were.  Mr. Violette said he received one by a citizen regarding a truck purchase but he didn’t have an exact answer; Mr. Violette will forward the question to the members.  Martha Mical noted that these questions should be discussed in the public forum.  Selectman Karrick recommends when an email is sent all members should be copied as well as the Town Administrator.  

Motion was made and seconded to adjourn at 7:40 p.m.

 

Respectfully submitted,

Mary Whalen

Recording Secretary