Town of Warner –Planning Board

Work Session Minutes

September 20, 2010      7:00 PM

Warner Town Hall , Lower Level  

 

Members Present:     Barbara Annis, Paul Violette, Rick Davies, Dan Watts

                                    and Ed Mical.

Members Excused:    David Hartman, Hank Duhamel

Members Absent:      None

Members Arriving Late: None

Alternates Present:    J.D. Colcord and Clyde Carson

Alternates Arriving Late: None

Alternates Excused: Peter Wyman, Aedan Sherman

Alternates Absent:  None  

OPEN MEETING AT 7:00 PM

ROLL CALL  

The Roll call was taken at 7:00 PM. Barbara Annis opened the meeting. Barbara Annis elevated J.D. Colcord to a voting member.  

1. PRESENTATION OF CIP TO BOARD OF SELECTMEN AND BUDGET COMMITTEE  

Budget Committee Roll Call:

Members present: Marc Violette, Martha Bodnarik, Mike Cutting, Alfred Hanson, Kimberly Brown-Edelmann and
Clyde Carson (Selectmen’s rep)

Not present:  Peter Savlen and Paul DiGeronimo  

Board of Selectmen present: Clyde Carson

Board of Selectman not present: David Hartman and David Karrick  

There is no quorum for the Board of Selectmen.  

Ed Mical made a short Power Point presentation for 2011-2016 CIP.  

Ed Mical recognized the members of the CIP subcommittee: Aedan Sherman, Peter Wyman, David Karrick, Martha Bodnarik, Jeanne Hand, Laura Buono, and Ed Mical.  

Ed Mical explained the same criteria were used as in the past. One of the criteria that the project should be consistent with Warner’s Master Plan has not been followed closely in the past couple years since the Master Plan is being updated. Ed Mical said the CIP projects should be tied in to part of the Master Plan.  

THE CIP PROCESS  

  1. The Planning Board CIP subcommittee is formed, following the Town Meeting and consists of representatives from the Planning Board, a representative from the Budget Committee, and a Selectman.  Additional participants will be drawn from the public at large.  A Planning Board representative will be Chairperson and coordinate all activities.
  1. The CIP Subcommittee, through the Planning Board Secretary, delivers information and application materials to all Town department heads, Board/Commission Chairs and the School Board.  Information included is a copy of their portion of the latest Master Plan and current CIP, a work sheet and the ranking criteria.  The Department heads submit their Capital requests with the priority rankings, estimated costs, the year for which they are seeking the request and identification of how each project/purchase is to be funded.  Additionally, all priority ranking work sheets need to be submitted.
  1. The CIP Subcommittee collects the requests, reviews the narratives and priority rankings and compiles them into this document for review by the Planning Board.

Ed Mical said there were three CIP Subcommittee meetings. The Public Hearing was held at the September 13, 2010 meeting of the Planning Board where a vote was also taken by the Planning Board to accept the CIP as presented. The Final CIP was signed by the Town Clerk on September 15, 2010 .  

Ed Mical said there were 24 projects included in the 2011-2016 CIP. Ed Mical said there were some Departments that did not request any projects this year: Cemeteries, Merrimack County , and Kearsarge Regional School District .  

Ed Mical presented a summary of the projects in the 2011-2016 CIP through the Power Point Presentation. Some of the projects were talked about in more detail. Ed Mical explained the repair of the granite steps in front of the Town Hall cost was changed from the original request of $20,000 to $11,000 due to a recent price quote obtained. The current boiler in the Town Hall is approximately 40-45 years old and has had issues; therefore a request has been made to replace it in 2011. The CIP committee requested more information on the energy upgrades to Town owned buildings; therefore the project was not recommended.  

Marc Violette questioned the ranking for the energy upgrades. Ed Mical said the committee agreed with the Departments requesting the projects ranking. He said rather than changing the ranking the subcommittee put in comments. Martha Bodnarik said the subcommittee did not recommend the project since they did not recommend the libraries similar request from last year without definite costs. It was decided for consistency sake to reject the Board of Selectmen’s energy upgrade request for the same reason.  

Ed Mical continued with his presentation. He said the cost of the Police Department cruiser replacement was cut down to $16,000 each year for two years since the price of the new cruiser was less expensive. The projection will be $18,000 for 2014 and 2015. Mike Cutting confirmed they were requesting $16,000 for 2011 and 2012. Ed Mical said that was the projection. Ed Mical said the information for the six years is in the provided spreadsheet.

Mike Cutting said he found a discrepancy in the Total Town only cost in 2011 as compared to the total amount contained on page 23 of the CIP. Mike Cutting asked if they are going by the total recommended amount for 2011 or the total requested amount. Ed Mical said the total recommended amount. It was verified that amount was correct.  

A brief discussion was held regarding the new Fire Station that is projected for 2014. The land status was discussed and the cost to build a fire station. Clyde Carson said more information will be available in the near future.  

Ed Mical spoke about the request for new radios and pagers for the Fire Department. In January 2013 all radios must meet the new narrow band requirements. He said the new radios will be okay but the older radios cannot be retrofit so they will need to be replaced. There are a few pagers that will also need to be replaced. Ed Mical added that the Highway Department will also have the same issue. Any Town radio will need to meet the new narrow band requirements. Mike Cutting asked if grant money would be available. Ed Mical said yes but the radios that are covered by grant monies are very expensive and the Town does not need to spend that amount of money per radio; they can get 3-4 radios for the same amount of money. Ed Mical said the Fire Department has some radios that are already compliant, however, once the change becomes in effect those radios will need to be reprogrammed so there will be some fees associated.  

Alfred Hanson asked about the Police Department radios. Ed Mical said they will also need to have their radios reprogrammed. He said it is his understanding that those funded by the grant from the State, the State of NH will take care of the programming. He said it is more the Highway Department and Fire Department that will have the issue.  

Mike Cutting said radios and pagers have been bought right along. Ed Mical said only pagers were purchased. There were a few radios received through a State grant over the past couple years that are compatible with the narrow band requirements. Mike Cutting asked if there is any value in the old radios. Ed Mical said no because they will not be able to be used at all per the FCC regulations.  

Ed Mical said listed in the CIP over the years there has been a replacement schedule for the cruisers and for the Highway Department trucks; however, there has never been a replacement schedule with cost estimate for fire apparatus so this has been added. Ed Mical explained that due to limited money in the Capital Reserve Fund the Town was forced to pay the entire cost of the new pumper approved at the 2010 Town Meeting. Ed Mical said the idea is to start putting money into a Capital Reserve Fund for Fire Department vehicles. A brief discussion was held regarding the life expectancy of the vehicles. Ed Mical said on average it is 20 years.  

A few other projects briefly discussed were: dry hydrants, highway department construction fund as well as bridges, and Highway Department truck replacement schedule.  

Ed Mical said photos were added to the CIP. The Retreat Road project of the Highway Department was included in the photos.  

A lengthy discussion was held regarding an alternate route off of Kearsarge Mountain Road . A request was made for $50,000 to cover a study to find the best route. Mike Cutting said he thought engineering was done when Split Rock was being constructed. Barbara Annis said there was a spur coming off of Split Rock but it never developed.  Barbara Annis said the Town never did engineering for the alternate route at that time. J.D. Colcord confirmed it was never engineered by the Town but rather Allan Brown looked at it.  

Alfred Hanson asked about Pattee Road being considered as an alternate route in the past. Mr. Hanson felt it was not necessary to put money aside for a project that will not be done in the near future since the Town does not own a right of way through that area. He feels that if someone buys that commercial piece of land they will need to put in a road to develop the land. Mr. Hanson feels the money will be better used somewhere else. Martha Bodnarik said before putting away that kind of money the Planning Board and Selectmen should think if they are willing if necessary to exercise the right of eminent domain. She said if the Town is not willing to do such a thing then the study should not be done. J.D. Colcord said that would be a decision the Selectmen and Budget Committee to make. He said it is their choice if they want to fund the $50,000 for the study or not. Ed Mical said this project has been submitted to the CIP for 4-5 years and Allan has talked about for years. The project was addressed in the 1999 Master Plan.  

Paul Violette said this is only a recommendation. The Budget Committee and Board of Selectmen do not have to fund the project. Ed Mical said it is a project submitted by Emergency Management just like any other project submitted. It is a life safety issue.  

Paul Violette said even if it was decided to fund the project and 3-4 years down the road it was decided not to do the alternate route they could get a change of purpose through a Town vote for any monies in the Capital Reserve Fund.  

Mike Cutting asked if the Planning Board had investigated the cost of the study. Ed Mical said this project was not submitted by the Planning Board. Emergency Management had received an estimate a couple years ago with a ball park figure of $30,000-$50,000.  

Dan Watts said he agreed with the comment that if we are not going all the way in terms of taking the land to put in a road then spending the money on a study next year would be like tossing away good money. Ed Mical said this may never happen however it is listed in the CIP as a project.  

Alfred Hanson asked what the Road Committee thought of the project. Ed Mical said they have not looked at it they are working on existing roads.  

Ed Mical continued with his presentation on:  

The Transfer Station requested: Equipment replacement. Martha Bodnarik questioned the requested amount being changed from $13,000 to $10,000. Ed Mical said the CIP subcommittee lowered the amount because they were considering using the current machine as a trade. Clyde Carson said the Transfer Station Committee came up with the recommended $13,000 based on the equipment needs out through 2015. Clyde Carson said that originally the request was for $10,000 but then they decided to request $13,000; Parks and Recreation (mower replacement). Martha Bodnarik said she thought they should be looking at the $13,000. The other request was for the expansion of loading dock area. The subcommittee recommended taking the left over money from the land purchase to put towards the expansion.  

Parks and Recreation placed a request for a replacement mower. Originally a higher figure was requested; however, the amount was lowered after a new bid was submitted. The amount was lowered from $15,000 to $12,000.  

Pillsbury Free Library submitted a request for $13,800 for energy upgrades for 2011. A computer upgrade request was submitted for $10,000. Mike Cutting asked if they could work that into their normal operating budget. Ed Mical said that was discussed in length at the Planning Board presentation. He explained that the Library had used their funds for repairs. Since the Town’s revaluation was lowered the Library will have a decrease of $5,000 to $7,000 in money received from the Town. Marc Violette said the Library as of today is not sure what amount they will have. The amount will be known shortly.  

The CIP subcommittee did not recommend funding the Conservation Request of $50,000 for 2011 due to the economy. The request is for $50,000 each year over the course of 5-6 years.  

The Planning Board requested $10,000 for a more comprehensive study to be done in the Exit 9 area for traffic control improvements. The subcommittee recommended $5,000. Martha Bodnarik asked if the project qualified as a Capital Improvements Project since it was under $5,000. Ed Mical said yes since the request from the Planning Board was for $10,000.  

The Warner Water District did not make any request for 2011. The previous projects submitted for 2014 are still included in the 2011-2016 CIP. The only change was a reprioritization of projects.  

Ed Mical said the Kearsarge School District had no projects listed at this time because their budget process is just starting and they are not ready in September for the CIP. The School Board and the Budget Committee do not meet until September/October so their time frame to get a request would be late November or early December. The CIP subcommittee made a recommendation that an addendum could be put into the CIP to show what the District was looking to do around December time frame. Marc Violette agreed with the time frame.  

Marc Violette verified that the CIP subcommittee recommended total projects amount of $569,800 is the number they are looking at. Ed Mical said yes.  

Mike Cutting asked if the Departments are in agreement with the recommended amount. Paul Violette said the Planning Board did not come up with that amount. The recommended amount comes from the CIP subcommittee. Barbara Annis said she did voice her opinion on the decrease in funds for the Exit 9 area. Martha Bodnarik said as a committee member she knows the Department heads do not have a chance to say how they feel until the budget process starts.  

Alfred Hanson questioned why the Fire Department does not have a yearly amount going into a Capital Reserve Fund for the new station since this is a project that will be done in the near future.  

Ed Mical said a new thing added to the CIP this year was an Expenditure Sheet for the past few years. Ed Mical explained as agents the Selectmen can spend the money in the Capital Reserve Fund without having to go before Town meeting for approval. The addition of the Expenditures shows what has been spent over the past few years.  

Barbara Annis said it bothers her that the Selectman can use the Highway Construction Capital Reserve Fund (CRF) as an operating budget to repair roads. She said a CRF is used to accumulate monies for a big project down the road. She asked why it is not added into the operating budget to show the Town what is actually going on. Martha Bodnarik agreed if the money is expended every year it would make it an operating budget rather than CRF.  

Ed Mical said they are spending a portion of it every year not the full amount. Mike Cutting said that is the critical part if only part of it is spent it is still a CRF. Barbara Annis said as part of the operating budget what was not spent could be encumbered. Clyde Carson said the Selectmen are limited to what they can encumber. If the money is encumbered you need to have a pending bill or you lose it. Using the Highway Construction CRF they can decide which projects need to be done and still keep the left over money to work on another project at a later time. Clyde Carson said he does not foresee ever running out of projects to use that CRF for.  

Alfred Hanson said the available money for the Fire Station is only $206,000 in Capital Reserve Fund. He asked is the money for land or the building.  Mike Cutting said the money is put away for building or expanding the Fire Station which could be used to purchase land, build with, as long as it used for a fire station. The money cannot be used to buy a fire truck. Alfred Hanson said for 2011 the Fire Department is requesting $30,000 for vehicle fund but no money requested for a Fire Station. Alfred Hanson said they see something they know is going to happen and they see things they do not think will happen; he cannot understand the logic of putting money aside for projects that may not be done instead of putting it away for an imminent project. Mike Cutting said a few years back it was agreed to not add anymore money to the Fire Station building fund until an actual site or proposal was submitted.  

Alfred Hanson said his point is that putting away $50,000 for an alternate route on Kearsarge Mountain Road that they do not know anything about does not make sense when they could take $50,000 to put toward the building fund for the Fire Station. J.D. Colcord said the request for the alternate route is not for building it but rather for a study to find where the best location for the alternate route would be. Alfred Hanson said he is surprised that it would cost $50,000 to conduct a study. Paul Violette said that you do not know what you will run into for example any wetlands that would involve DES , therefore $50,000 could be a realistic price. Martha Bodnarik asked if the alternate route would interfere with the current conservation easement and if a road could be put through one. Paul Violette said he does not know. Barbara Annis said maybe it should be done now before the conservation land is expanded even further.  Alfred Hanson said he just wants to be sure the money is put towards the most logical project.  

Ed Mical said some of the members of the Fire Department along with the building committee had contacted some architectural firms to come up with a packet of what is actually needed for a fire station as well as coming up with some realistic costs. Alfred Hanson asked if this process was costing money. He was told yes. Paul Violette said the architect is coming up with early concepts and costs estimates and what is required by NFPA, ADA , etc. in terms of codes and standards. Paul Violette said they will probably apply for a Federal grant to help offset the cost. A brief discussion was held about the project and the hiring of an architectural firm as far as the needs of Warner’s Fire Department and the option of bonding. It was understood that the architectural firm was hired to do a conceptual plan.  

Paul Violette said back to Alfred Hanson’s point about the alternate route on Kearsarge Mountain they do not know what is going to happen however they do know the fire station will cost more than $250,000 therefore it would be a worthwhile project to save money for.  

Ed asked what the Budget Committee thought of this year’s CIP with the new changes. Marc Violette said he thought it was well presented as well as clear and precise. It was agreed by all the CIP is a great tool to provide an overview of all department requests.  

A copy of the 2011-2016 CIP will be sent to all Department heads.  

2. DISCUSSION OF GRAVEL PIT ORDINANCE AS RENEWAL OF APPLICATIONS WILL BE DONE IN DECEMBER  

Barbara Annis said there are three gravel pits in the Town: Courser, Hill and Warner Aggregates. All permits expire December 31, 2010. She said there have been times it has taken more than one meeting with the applicant to approve the permit. Barbara Annis asked what the Planning Board requires from the applicant so they can be prepared when they come before the Board at a regularly scheduled meeting to renew the permit.  

Paul Violette asked if they are proposing making changes to the Earth Excavation Ordinance. Barbara Annis said no they are not changing the regulations.  

J.D. Colcord said he would ask if the Selectmen or Conservation Commission see anything that might be happening at the gravel pits that may be a problem such as hitting ground water, etc.  

Barbara Annis said she checked to see if the applicants needed to do a new plan, etc. She read aloud a section of the regulation:  

Permit holders wishing to alter the size or location of the excavation, the rate of   

            removal or the plan for reclamation shall apply for a renewal or amendment,                             

      following the same procedures as those required for the original excavation permit.  

            Permit holders wishing to renew a permit where there are no changes to the permitted operation may do so by requesting a renewal from the Planning Board. The Planning Board may approve such a request without a public hearing if it finds the operation to   be in compliance with all current plans and narratives describing the operation.

 

Paul Violette asked if they should ask the Board of Selectmen and Conservation Commission in writing if they have any problems with the gravel pits. Clyde Carson said the Selectmen are not aware of the renewals coming up.  

Barbara Annis said she would like each permit holder to receive a formal letter from the Planning Board stating the expiration date, if they wish to renew the permit please apply to the Planning Board for a renewal of the permit, advise if there are any changes in the property from the previous permit, if there are changes what are they, etc. Barbara Annis said she would like to see it in writing from the permit holders before sharing information so the Board, the Selectmen and Conservation Commission have the information in front of them provided by the permit holders.  

Paul Violette said he agrees that the information needs to come from the permit holders.  

Clyde Carson asked how long the renewals are for. Barbara Annis said three years.   

Ed Mical said the intent to excavate is signed by the Selectmen.  

J.D. Colcord said it would be useful if he knew the Conservation Commission was satisfied with the way the gravel pits were conducting excavation, cleaning up after themselves, reseeding, etc.  

Dan Watts asked who certifies they are in compliance. He asked if the Selectmen are the certifying agents. Clyde Carson said he is not sure. Everyone agreed the Conservation Commission would be a good choice for this.  

Ed Mical said they could compare the Intent to Excavate with the plan quantities to see how they match up.  

Clyde Carson asked if the Town gravel pit was subject to the same rules. The Town gravel pit is subject to different rules.  

The Board agreed to send a letter to the three gravel pit permit holders as well as a letter to the Conservation Commission and the Board of Selectmen asking them to review the information. Clyde Carson suggested giving the Boards a date to give feedback by. Paul Violette suggested the permit holders not only provide a desire to renew but also a summary of their activity over the past three years. J.D. Colcord said Martha Mical would have that information. It was suggested to give the information to the Conservation Commission for their review.  

Clyde Carson asked what is the sequence of events for approval. The Planning Board approves a permit to have a gravel permit; Martha Mical, Assessing Clerk, provides the Intent to Excavate; and then the Board of Selectmen sign the Intent to Excavate.  

3. SUBCOMMITTEE REPORTS  

A. CDPC  

The subcommittee minutes of September 8, 2010 were approved.  

A meeting will be scheduled in the near future to continue discussions.  

Dan Watts had some feedback for the subcommittee. He suggested that the committee for consistency keep to either gross floor area or footprint. He also suggested when talking about the total land for Commercial Districts that the percentage be used throughout as well as acreage to tie them together.  

Paul Violette said it is a work in progress. They are working on draft warrant articles with an easy to understand rationale.  

Most of the discussion is on the Davisville area as well as discussions on the maximum building area and height requirements for a pitched roof.  

LED lighting has been briefly discussed. Dan Watts said his only concern is having wording that will not be a first amendment issue by limiting what is said. He said Concord ran into that problem and had to do away with it completely. If you limit it to numbers only someone could say a restriction cannot be put on their speech so LED would be everywhere. It may be able to be focused specifically to gas stations.  

Dan Watts said he likes the new Shell sign with the backlit numbers. It can be easily seen coming off the highway.  

Rick Davies asked if there will a subcommittee to look at the sign ordinance. Barbara Annis said maybe next spring after they get through the Site Plan Regulations, Subdivision Regulations, and Zoning Ordinance as well as the Public Hearing. The Board of Selectmen have requested that the sign ordinance be looked at also.  

Barbara Annis said there is miscommunications between the various Boards and Departments causing misinformation to be given out. She feels the Zoning Ordinance is clear.  

Dan Watts worked on a definition for Major Subdivision in the Zoning Ordinance. A short discussion was held regarding the current definition of a Major Subdivision and a Minor Subdivision.  

Rick Davies said he was also looking at if an office building is attached to a warehouse they are two different use types what should the square footage be.  

B. Transportation Committee Exit 9 Area  

Paul Violette wrote a letter requesting RPFP/RFQ from approximately 8-10 engineering firms but only one answered.  

Paul Violette said Holden Engineering dropped off a packet to the Planning Board with an overview of the project as well as a schedule. Barbara Annis said a copy is available in the Land Use Office and the Board Selectmen’s Office.  

Paul Violette said the time schedule in the packet will need to be revised.  

J.D. Colcord said he understood that it would be determined what type of option was wanted there and have Market Basket help with the costs as they proceed with any new plans.  

Barbara Annis said she disagreed with that idea. Barbara Annis had the secretary contact the Concord Planning Board to ask what their procedure is regarding road safety issues. The Concord Planning Board stated that if a business is going to create a large increase in traffic flow the developer is required to conduct a traffic study and the impact fees go towards the traffic light or whatever they need. If there is money in long term capital improvements then that is credited to the work.  

J.D. Colcord said in sitting in Concord for six years in the cases he saw the developers paid it all. Barbara Annis said she would contact, Ed Roberge, the engineer in Concord . J.D. Colcord said that is also what he was told by a member of the Concord City Council when he asked the specific question, who pays for improvements?  

Paul Violette said there is potential for expansion in the Market Basket property that would create  heavier traffic in the area.  

A brief discussion was held regarding the pros and cons of impact fees and exaction fees.  

Barbara Annis said she feels the Town needs to encourage growth at the Market Basket area to help with the Tax base as well as helping unemployment in the area. She said she can remember the Selectman working with Jordan Milton by having them pay half the taxes on half of their assessment the first year. Barbara Annis said sometimes you need to give a little something to get something.  

The Board agreed to send a letter to Don Gartrell, Market Basket attorney, requesting a meeting to discuss the traffic issues in the areas. Paul Violette agreed to compose the letter.  

A meeting has been scheduled for Tuesday, September 28, 2010 at 10 am at the Town Hall.  

C. Site Plan Review Committee  

Barbara Annis said the subcommittee has not had a chance to get together since their last meeting. A meeting will be scheduled in the near future.  

Barbara Annis said she sent Ed Mical a copy of the latest draft of the Site Plan Regulations with proposed changes. She said the only problem she sees is the Board is trying to make it so every applicant does not have to come before the full Board for every site plan review, but the regulations still read a change of land use is determined by “the Board” and the ‘the Board” makes a decision. Looking at other towns it all depends on the situation if they are required to go before the full Board. Barbara Annis said some of the towns have in their regulations a committee will determine whether the application needs to go before the full Board and others delegate the responsibility to the City Planner, a Planner from Central New Hampshire for the town, etc.  

If a committee is created to make the decision if an applicant needs to go before the full Board it would need to go before Town Meeting before being created. Rick Davies asked who would be on the committee. J.D. Colcord suggested Chairman of Planning Board, Chairman of Board of Selectman and the Land Use Secretary.  Barbara Annis said she was thinking the Planning Board Chair, Zoning Board of Adjustment Chair and possibly the Building Inspector.  

Paul Violette said the idea was to make it a less lengthy, cumbersome process for someone to move into a space that was just recently vacated. Paul Violette said it probably is not a big issue for someone to wait 15-20 days from the time they apply to the time of approval from the Planning Board.  

Barbara Annis said she would prefer to have everyone take the responsibility of approving or disapproving an application rather than just one person.   

Paul Violette said it may be better to have an applicant come before the Board to explain what they want to do and give the Board the option to waive the Site Plan or have them return with more details.  

Paul Violette asked if a more streamline approach could be limited to the B-1 Zone. In the B-1 Zone a designated representative could make the decision if a Full Site Plan is required. Barbara Annis asked the Land Use secretary if she would want the responsibility. She said yes. Paul Violette said there will need to be some criteria that can be followed.  

A short discussion was held on the Use Table. The Board agreed the Use Table in the Zoning Ordinance was just put together without any ranking system.  

Rick Davies said he is worried about a grey area and he would not like to see one person take on the responsibility. J.D. Colcord said he would prefer to see the Land Use secretary make the call and if a mistake happens then it can be dealt with and move on.  

The Land Use secretary, Tracey Hallenborg, suggested having a short application for Site Plan Reviews that everyone would need to fill out with key questions such as hours of operation, parking impact, outside storage, is a building permit required any life safety issues, etc that would stand out as an impact on the Town. At that point if there is no significant impact then the secretary could sign off on the application. If the application is questionable it could go before the Board at a Work Session meeting under communications to be reviewed by the Board if a full Site Plan is required; if one is required there is still time to send notices to abutters, place an ad in the paper and schedule the applicant for the upcoming monthly meeting. If there is an obvious impact then the secretary would schedule the applicant at a regular Planning Board meeting. The secretary also stated that the application would kept on file and if the applicant did anything different there would be a signed record that the Planning Board could refer to and have them come before the Board if necessary.  

The Board agreed that a signed short application would be a good idea.  

D. Board of Selectman Report  

Clyde Carson said the Governor is coming to Town Wednesday September 22, 2010 for the Executive Counsel Meeting.

4. COMMUNICATIONS AND MISCELLANEOUS  

Rick Davies said he received an e-mail that the Selectmen were concerned about the subcommittees meeting at other places rather than the Town Hall. Clyde Carson said the Selectmen are requesting subcommittees to meet in the Town Hall if space is available. Paul Violette asked if there were any complaints from anyone not being able to find a meeting. Clyde Carson said no.  

5. PUBLIC COMMENTS  

No public was present.  

6. ADJOURN  

J.D. Colcord made a MOTION to ADJOURN. Paul Violette seconded the MOTION and all were in favor. The meeting adjourned at 9:30 PM .